Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF)

  • A method for objectively ranking and sequencing Product Backlog items
  • Ensures items of highest value are delivered at the earliest opportunity.
  • Value is based on cost of delay. Items with highest Cost of Delay and lowest cost of development (effort) are ranked higher for delivery
  • When 2 items have the same value, do item with lowest cost (effort)
  • Provides teams with clarity about what to be working on
  • Minimizes work in progress.
  • Does not rely on absolute number estimates – each backlog item is ranked relative to others

WSJF Calculation

  • WSJF = Cost of Delay (COD) / Job Size (Effort), where
  • COD = Business Value + Time Criticality + Risk Reduction Opportunity
  • Rank = COD/Job Size (Effort)

WSJF parameters for each feature are scored relative to all other features using Fibonacci (0,1,2,3,5,8,13…).

WSJF Calculation Example
WSJF Calculation Example

Do scoring for one column at a time for all features before moving to next column. Start by finding smallest ranked item and giving it a 1. There must be a 1 in each column. In the above example, Feature B should be delivered first, followed by Feature A, then Feature D.

As an aside, the idea of connecting features to business value can be visualized using a ‘Value Driver Tree’ approach. This is a good way to address the question: Why are we building this feature, what’s the business value.

Connecting Features to Business Value
Connecting Features to Business Value
References:

Principles of Product Development Flow, Donald Reinertsen

What is Business Value?

Measuring Value with KPIs

 

Print Friendly, PDF & Email

Similar Posts